Rio2 quarterly shows dual-mine production muscle in South America
Diversified producer Rio2 has flexed its production muscle in South America, delivering a solid June quarter from its dual-asset portfolio that churned out a consolidated 13,539 ounces of gold, 75,437 ounces of silver and 9.3 million pounds of copper.
The impressive production figures from the company’s Fenix gold mine in Chile and its Condestable copper-gold-silver mine in Peru generated a handsome US$76.2 (A$107.5) million in earnings before interest, tax, depreciation and amortisation for the three months ended June 30. Adjusted EBITDA came in at a still-hefty US$46.5M(A$65.5M).
The company’s Condestable mine in Peru continued its role as the steady cash-generating workhorse, delivering solid operating performance and processing over 700,000 tonnes of ore. For the quarter, it produced 9.29 million pounds of copper, 4451 ounces of gold and 74,374 ounces of silver, contained in concentrate.
The operation is underpinned by a recently updated mineral reserve estimate that points to a serious long-term asset. A June update outlined total proven and probable reserves of 36.5 million tonnes grading 0.73 per cent copper, 0.15 grams per tonne (g/t) gold and 4.28g/t silver.
Notably, those reserves support a robust post-tax net present value of US$710 million (A$1B) at an eight per cent discount rate and a 14-year life of mine.
Notwithstanding this solid foundation, Rio2 is already exploring ways to expand the Peruvian mine. It has launched a three-part exploration program for 2026, including a 46,480-metre underground diamond drilling campaign to replace and augment resources. The company is also looking to improve the grades through ore sorting and is planning a plant expansion to 10,000 tonnes per day.
Meanwhile, at the Fenix gold mine in Chile, Rio2’s major growth project, the ramp-up is progressing well with the company on track to achieve full commercial production in the fourth quarter of this year.The project lies in the prolific Maricunga gold beltand recently transitioned from development into production. The heap leach operation hosts a staggering 389 million tonnes of ore grading 0.38g/t gold, for a total of 4.8 million measured and indicated ounces.
The heap leach operation produced 9088 ounces of gold during the quarter, with ore mining rates increasing from 13,600 tonnes per day in April to 16,100 tonnes per day in June. The company expects to hit a 20,000-tonne-per-day ore processing rate during the current quarter.
Rio2 says key start-up constraints have been identified and addressed, including the successful transition to a new larger-capacity mining fleet. Unusually cold weather and significant snowfall presented some challenges late in the quarter, however, management says the onsite crew is handling the conditions well, maintaining leaching and plant operations.
Rio2 Limited president and chief executive officer Andrew Cox said “ At Fenix Gold, operational performance continued to improve during the quarter with more work areas opened, more people employed and the arrival of the principal mining contractor’s mining equipment, all of which we anticipate will make a meaningful impact to productivities and costs during Q3.
5News aggregated this summary from the outlet’s public feed. The full article, with all the context, is on www.brisbanetimes.com.au — the content belongs to Brisbane Times.