Harrdy Sandhu’s ‘Stuck On You’ to get 72-hour subscriber-first release in India Esha Deol turns Sunny Deol’s “Dhaai Kilo Ka Haath” into a Raksha Bandhan gag in Instamart campaign, watch Varun Dhawan fronts Fossil’s new machine X-1 collection, priced at Rs 40,995 Sunita Ahuja withdraws divorce case against Govinda, visits Mumbai family court with son Yashvardhan Actor Vikram video case: 11 exotic animals likely to be shifted to Vandalur zoo Exclusive building sought for BC Study Circle in Vizianagaram APNRTS appoints Billu Chandrasekhar as UAE Coordinator Abhimanyu murder case: Ernakulam Sessions Court to announce schedule of trial on August 21 New bus stops, route changes planned after KBR Park one-way traffic rule BWF Worlds: Shetty, Sindhu into pre-quarters; Lakshya, Unnati suffer exits Harrdy Sandhu’s ‘Stuck On You’ to get 72-hour subscriber-first release in India Esha Deol turns Sunny Deol’s “Dhaai Kilo Ka Haath” into a Raksha Bandhan gag in Instamart campaign, watch Varun Dhawan fronts Fossil’s new machine X-1 collection, priced at Rs 40,995 Sunita Ahuja withdraws divorce case against Govinda, visits Mumbai family court with son Yashvardhan Actor Vikram video case: 11 exotic animals likely to be shifted to Vandalur zoo Exclusive building sought for BC Study Circle in Vizianagaram APNRTS appoints Billu Chandrasekhar as UAE Coordinator Abhimanyu murder case: Ernakulam Sessions Court to announce schedule of trial on August 21 New bus stops, route changes planned after KBR Park one-way traffic rule BWF Worlds: Shetty, Sindhu into pre-quarters; Lakshya, Unnati suffer exits
India News

Mud, slush accumulate in Uttarkashi tunnel due to seepage, raise safety concerns

Hindustan Times - India News ·
Mud, slush accumulate in Uttarkashi tunnel due to seepage, raise safety concerns

Water seepage from the left-side wall of the 370-metre-long Tambakhani tunnel at the entrance to Uttarkashi town in Uttarakhand has led to water, mud and slush accumulating along the pedestrian walkway inside the tunnel.

Border Roads Organisation (BRO) executive engineer Sumit Verma said that after the management of the tunnel was transferred from the irrigation department to the BRO more than five months ago, the organisation had written to the government seeking the services of a specialised technical agency.

“The agency will conduct an in-depth hydrological and engineering study of the subterranean seepage. Permanent structural repairs will be undertaken based on the findings of the study. The Detailed Project Report (DPR) and tendering process has been completed,” Verma said.

Also Read: Uttarakhand inundated tunnel toll rises to 9 as rescue operations continue

Residents said that the tunnel, constructed in 2013 at a cost of approximately ₹ 19 crore near the Uttarkashi district headquarters, has faced persistent water seepage problems since its construction, with the situation worsening during the monsoon season.

“The water seepage is not new and has occurred for the third time in four years. If not repaired, it poses a threat not only to the tunnel but also to human lives as it is the gateway to the Gangotri shrine from Uttarkashi,” said Dharmendra Singh, a resident.

Addressing concerns over the delay in permanent repairs, BRO Commander Raj Kishore said a formal proposal for preparing a DPR for comprehensive rehabilitation of the tunnel was submitted to the Ministry of Road Transport and Highways.

Kishore said that the selection of a construction agency through a competitive bidding process is currently underway. A specialised technical agency was also tasked with carrying out a detailed hydrological and engineering assessment of the seepage, following which permanent repairs would be undertaken based on its recommendations.

Also Read: Uttarakhand: Landslide damages bridge in Pithoragarh, Dharchula-Gunji traffic closed

Suresh Chauhan, an MLA from Gangotri, said the affected portion of the tunnel was treated in the past but the seepage intensified during the monsoon. “The management of the tunnel has now been transferred to the BRO and clear instructions have been given to conduct a study and ensure a permanent solution to the water seepage problem,” he said.

President of Uttarkashi Hotel Association Shailendra Matura said the latest rupture along the left flank of the tunnel had resulted in a steady flow of water.

“The absence of adequate lighting and accumulation of slush pose a serious risk to people walking through the tunnel. The government should find a permanent solution, otherwise the problem could turn into a major fiasco in the near future,” he said.

Read the full article on Hindustan Times - India News ›

5News aggregated this summary from the outlet’s public feed. The full article, with all the context, is on www.hindustantimes.com — the content belongs to Hindustan Times - India News.

More from Hindustan Times - India News

See all ›

More in India News

See all ›