NTPC terminates ₹413 crore BESS contract as contractor fails to meet obligations, achieve progress
Account subscription benefits alongside Premium Stories, Editorials, Opinions and more. Unlock these with Subscription
State-owned power producer NTPC Ltd informed that it has terminated the contracted awarded to GR Infraprojects Ltd (GRIL) for building the 400 Megawatt-hour (MWh) battery energy storage system (BESS) project at its Mouda Super Thermal Power Station (Maharashtra) citing the latter’s inability to meet their contractual obligations and achieve required project progress.
The project – with a contract value of ₹413.37 crore – was awarded in March this year and was scheduled to be completed within fifteen months.
Explaining the cause for terminating the contract, NTPC stated, “The project witnessed significant delay in critical activities. A contractual notice was issued to GRIL calling for immediate corrective action, but GRIL failed to undertake the required remedial measures.”
NTPC added that it has encashed approximately ₹91 crore from the bank guarantees.
The power producer added that it has re-initiated re-tendering of the project.
“NTPC is taking necessary measures on priority to facilitate the early re-award and timely implementation of the project,” it stated.
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.
5News aggregated this summary from the outlet’s public feed. The full article, with all the context, is on www.thehindu.com — the content belongs to The Hindu.