Emraan Hashmi diagnosed with Influenza A and Swine Flu; postpones Bengaluru event SCOOP: Before Karna with Salman Khan, Rakeysh Omprakash Mehra to direct Vikrant Massey in a Love Story CBI court refers Dhayanidhi Alagiri to JIPMER for medical examination EPFO 3.0: Centralised database, UPI and ATM withdrawal options, quicker settlement — Changes for subscribers, explained Chennai Corporation Council meeting | Unlikely allies as parties unite against State govt. over lack of ward funds More measures needed to make Mangaluru Railway region friendly to commuters: Ivan D’Souza Nepal floods kill 669 as renewed rain hampers rescue efforts Revive dedicated minor irrigation system with modern technology: Farmers’ Commission Poll schedule for Tripura village committee elections to be announced Vice-President calls for research-oriented education Emraan Hashmi diagnosed with Influenza A and Swine Flu; postpones Bengaluru event SCOOP: Before Karna with Salman Khan, Rakeysh Omprakash Mehra to direct Vikrant Massey in a Love Story CBI court refers Dhayanidhi Alagiri to JIPMER for medical examination EPFO 3.0: Centralised database, UPI and ATM withdrawal options, quicker settlement — Changes for subscribers, explained Chennai Corporation Council meeting | Unlikely allies as parties unite against State govt. over lack of ward funds More measures needed to make Mangaluru Railway region friendly to commuters: Ivan D’Souza Nepal floods kill 669 as renewed rain hampers rescue efforts Revive dedicated minor irrigation system with modern technology: Farmers’ Commission Poll schedule for Tripura village committee elections to be announced Vice-President calls for research-oriented education
Latest

Bikarnakatte-Sanur project achieves 76.1% progress, says NHAI official

The Hindu ·
Bikarnakatte-Sanur project achieves 76.1% progress, says NHAI official

Account subscription benefits alongside Premium Stories, Editorials, Opinions and more. Unlock these with Subscription

The four-laning of the Bikarnakatte (Mangaluru)-Sanur (Karkala) section of National Highway 169 has achieved 76.1% progress, and the project is expected to be completed by March 2027, according to Abdulla Javed Azmi, Director, National Highways Authority of India (NHAI) Project Implementation Unit, Mangaluru.

Speaking at the District Development Coordination and Monitoring Committee (DISHA) meeting here on Saturday, he said that of the 45.01-km highway stretch being upgraded, 36.42 km is ready. The project, costing ₹1,137 crore, was originally scheduled for completion on October 8, 2024.

He added that work on a 1-km stretch near Rosa Mistica School at Gurupura-Kaikamba remains stalled due to a court stay order.

Mr. Azmi said the six-lane bridge project on NH 66 across the Phalguni River at Kulur has achieved 58% progress. One carriageway is likely to be completed by November 2026, and the entire project by May 2027. Launched on April 12, 2021, the project was originally slated for completion on October 11, 2022. The project cost is ₹69.02 crore.

Deputy Commissioner H.V. Darshan suggested that the NHAI conduct a joint survey with the district administration to identify and clear encroachments along national highways in the district.

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.

Read the full article on The Hindu ›

5News aggregated this summary from the outlet’s public feed. The full article, with all the context, is on www.thehindu.com — the content belongs to The Hindu.

More from The Hindu

See all ›

More in Latest

See all ›