The war in Ukraine and how the time of Gandhi became the time of Putin SINISTER PACT OP-ED: A not-so-odd couple: AfriForum and March and March’s dangerous alliance The bond market is beginning to revolt against America RESPECTED LEADER: Siya Kolisi brings gravitas as skipper for Boks in crucial second Test LEADERSHIP CRISIS: World Aquatics suspends Swimming SA president and CEO amid fraud and abuse-of-power claims MACABRE BUSINESS OP-ED: Shot, skinned and sold: South Africa’s enormous trade in wild primates RESILIENT RECOVERY: Brainstormed: How Kruger Park is rethinking the humble culvert PINE PAIN: Lower Tokai fynbos ‘can recover’, but scientists divided over what comes next POLL WARNING OP-ED: Elections and the information integrity crisis: Why SA’s human rights body is taking action Country icon Dolly Parton dead at 80 The war in Ukraine and how the time of Gandhi became the time of Putin SINISTER PACT OP-ED: A not-so-odd couple: AfriForum and March and March’s dangerous alliance The bond market is beginning to revolt against America RESPECTED LEADER: Siya Kolisi brings gravitas as skipper for Boks in crucial second Test LEADERSHIP CRISIS: World Aquatics suspends Swimming SA president and CEO amid fraud and abuse-of-power claims MACABRE BUSINESS OP-ED: Shot, skinned and sold: South Africa’s enormous trade in wild primates RESILIENT RECOVERY: Brainstormed: How Kruger Park is rethinking the humble culvert PINE PAIN: Lower Tokai fynbos ‘can recover’, but scientists divided over what comes next POLL WARNING OP-ED: Elections and the information integrity crisis: Why SA’s human rights body is taking action Country icon Dolly Parton dead at 80
Latest

RESILIENT RECOVERY: Brainstormed: How Kruger Park is rethinking the humble culvert

Daily Maverick ·
RESILIENT RECOVERY: Brainstormed: How Kruger Park is rethinking the humble culvert

To most visitors driving through Kruger National Park, a culvert is barely noticeable. It is simply the concrete structure beneath the road that carries water from one side to the other.

For infrastructure engineer Bharat Gulab, a culvert is where roads, rivers and a changing climate meet – and rebuilding one properly is a far bigger job than it appears.

Gulab joined SANParks in 2022 after working as a consultant and spending 10 years in the infrastructure department at Johannesburg Water. His work in Kruger has brought him face to face with the damage that extreme floods can cause to roads, bridges, buildings and management routes.

The park’s recent floods demonstrated the scale of the challenge. The estimated damage to infrastructure was about R950-million. Although insurance, government funding and SANParks’ own resources have covered part of the cost, the organisation still faces a shortfall of roughly R400-million.

The deeper challenge is that replacing damaged infrastructure exactly as it was is no longer enough.

Many of Kruger’s structures are already 50 or 60 years old. At the same time, Gulab says assessments of the park’s vulnerability show that floods are bringing volumes of water that existing infrastructure was never designed to handle. In some places, flood levels exceeded the line associated with a one-in-100-year event – the standard traditionally used when designing major bridges.

Reconstructing a culvert begins below the surface. Engineers first install subsoil drains beneath the structure. These give groundwater a controlled route out, preventing pressure and trapped water from weakening the foundation.

The road is then rebuilt carefully, layer by layer. At some damaged sites, teams have had to replace more than 5m of fill – the compacted material that supports the road and its approaches. It’s slow, precise work, but every layer helps the finished structure withstand the forces that arrive with the next major storm.

The approaches on either side of a culvert or bridge are just as important as the structure itself. During a flood, fast-moving water can scour away unprotected soil, leaving the concrete intact but making the road unusable.

At the Letaba high-level bridge, for example, the approaches had not been sufficiently protected and were badly damaged. The rebuilt approach now includes stone pitching and concrete drainage channels. These measures guide water away, protect the soil and reduce the risk that future floods will wash out the road again.

The same thinking is being applied to culverts on the Lower Sabie road. Some are being enlarged so they can carry greater volumes of water. Rather than forcing a swollen stream through an opening that is too small, the wider structures allow floodwater to pass more freely, reducing pressure on the road embankment.

This resilience does not come cheaply. Large culvert projects can cost more than R4-million each. Work on the Letaba bridge took about three-and-a-half to four months before traffic could cross again, with the full repair lasting close to six months.

Yet the investment protects far more than concrete and tar.

Read the full article on Daily Maverick ›